Production Planning
Machine-wise scheduling, daily capacity, and 2-week production outlook.
Total capacity / day
58
across 3 lines
Avg utilization
65%
last 7 days
Orders in plan
5
3 active
Plan buffer
6 days
next slot 18 May
Line A — Sliders
16 units/day
MV
Utilization82%
Line B — Casement
24 units/day
DP
Utilization68%
Line C — Fixed & Combo
18 units/day
MV
Utilization45%
14-day production schedule
Drag a bar to reschedule. Click to view order details.
Line
12
Tue
13
Wed
14
Thu
15
Fri
16
Sat
17
Sun
18
Mon
19
Tue
20
Wed
21
Thu
22
Fri
23
Sat
24
Sun
25
Mon
Line A — Sliders
16/day
Line B — Casement
24/day
Line C — Fixed & Combo
18/day
Capacity warnings
Line A — Sliders
Hits 100% next Tue with Surya start
Line B — Casement
Sound-rated glass arrival on 16 May blocks RHI
Line C — Fixed
Buffer day 14 May — can pull Mantri forward