B2B project umbrella spanning multiple orders, phases, and POs.
Active projects
5
4 multi-phase
Total project value
₹1.04Cr
across all projects
Avg duration
3.4 months
kickoff → handover
On-time delivery
92%
last 6 projects
Active projects (5)
Surya Hotels — Mowa Campus
Surya Hotels & Resorts
Started 19 Jan· Expected 30 Aug· PO SH/2026/INFRA/0142
₹41.0L
2 orders
Payment progress32%
Retention
5%
Sneha Park — Tower B
Sneha Builders Pvt Ltd
Started 12 Feb· Expected 15 Jul· PO SBPL/PRK/2026/008
₹17.8L
2 orders
Payment progress98%
Retention
10%
Khemani Family Residence
Ramesh Khemani Ji
Started 13 Apr· Expected 10 Jun
₹3.1L
2 orders
Payment progress56%
Agrawal Builders — Civil Lines
Sandeep Agrawal
Started 29 Apr· Expected 30 Jul· PO ABL/CL/2026/0042
₹15.5L
1 order
Payment progress20%
Retention
5%
Goenka Family Properties
Anjali Goenka
Started 10 Mar
₹2.1L
2 orders
Payment progress37%